RockSat-C 2018 Schedule

This schedule is subject to change, and this online version supercedes the schedule in the User's Guide. Presentation dates may vary from team to team. Questions can be directed to This email address is being protected from spambots. You need JavaScript enabled to view it.


Fall 2017 Schedule

TBD

Informational Teleconference for RockSat-C and RockSat-X

8/13/2017

RockSat Payload User’s Guide Released

9/18/2017

Deadline to submit Intent to Fly Form (IFF)

9/20/2017

Initial Down Selections Made, Welcome Package Sent Out

10/9-13/2017

Conceptual Design Review (CoDR) Teleconference

10/13/2017

Earnest Payment of $1,000 Due

10/30-11/3/2017

Preliminary Design Review (PDR) Teleconference

12/4-8/2017

Critical Design Review (CDR) Teleconference



Spring 2018 Schedule

1/10/2018

Final Down Select—Flights Awarded

1/22-26/2018

Progress Update Telecon

2/12-16/2018

Subsystem Testing Review Teleconference 

2/12/2018

First payment due

3/5-9/2018

Progress Update Telecon

3/26-30/2018

Integrated Subsystem Testing Review Teleconference

4/2/2018

Final payment due

4/9/2018

RockSat Payload Canisters sent to customers *pending receipt of final payment*

4/9-13/2018

Progress Update Telecon

4/30-5/4/2018

Full Mission Simulation Test Report Presentation Telecon

5/21-25/2018

Progress Update Telecon

5/30/2018

Possible Program Telecon

6/4/2018

Preliminary Check-In Procedure Document Due

6/4/2018

Launch Readiness Review Document Due 

6/13/2018

Travel to Wallops Flight Facility

6/14/2018

Visual Inspections at Refuge Inn

06/(15-18)/2018

Vibration/Integration at Wallops

6/20/2018

Presentations to next year’s RockSat

6/21/2018

Launch Day!!

7/13/2018

Preliminary Launch Results Document Due

7/27/2018

Final Report Due

 

 Indicates a deliverable

Indicates a group event/milestone

 Indicates an update teleconference

Indicates payment due