This schedule provides the dates for all deliverables and important deadlines for the 2015 RockSat-X program. This schedule is subject to change, and the last update was made: 07/24/2014. Launch date is still being determined. Questions can be directed to Jesse Austin at This email address is being protected from spambots. You need JavaScript enabled to view it.

RockSat-X 2014/2015 Schedule 

09/19/2014

Intent to Fly Forms (IFF) DUE

09/24/2014

Initial Down Selections Made/Welcome Letters Sent

10/13/2014

Conceptual Design Review (CoDR) Slides DUE

10/14/2014

Conceptual Design Review (CoDR) Teleconferences

10/17/2014

Earnest Deposit of $2,000 DUE

11/03/2014

Preliminary Design Review (PDR) Slides DUE

11/04/2014

Preliminary Design Review (PDR) Teleconferences

12/01/2014

Critical Design Review (CDR) Slides DUE

12/02/2014

Critical Design Review (CDR) Teleconferences

12/05/2014

Post CDR Action Item Generation

01/16/2015

Final Down Select—Flights Awarded

01/26/2015

Post CDR Action Item Review

02/16/2015

First Installment Due

02/16/2015

Subsystem Testing Review (STR) Slides DUE

02/17/2015

Subsystem Testing Review (STR) Teleconferences

02/19/2015

Experiment Decks and Connectors Sent to Customers

04/06/2015

Integrated Subsystem Testing Review (ISTR) Slides DUE

04/07/2015

Integrated Subsystem Testing Review (ISTR) Teleconferences

04/08/2015

Final Installment Due

04/13/2015

Full Mission Simulation Review (FMSR) Slides DUE

04/14/2015

Full Mission Simulation Review (FMSR) Teleconferences

05/05/2015

Weekly Teleconferences Begin

05/11/2015

Round 2 - Full Mission Simulation Review (FMSR) Slides Due

5/12/2015

Weekly Teleconference 2

05/12/2015

Round 2 - Full Mission Simulation Review (FMSR) Teleconferences

05/19/2015

Weekly Teleconference 3 (Procedure Walk-Through)

05/26/2015

Weekly Teleconference 4 (Travel Logistics)

06/02/2015

Weekly Teleconference 5 (Integration Readiness Review)

~06/23/2015

GSE Checkouts At Refuge

~06/24>28/2015

Testing and Environmental With Wallops

06/30/2015

Weekly Teleconferences Resume

07/20/2015

Launch Readiness Review Packages (LRR) DUE

07/21/2015

Launch Readiness Review Telecons with Wallops

~08/04/2015

GSE Checkouts at Refuge Inn

~08/05>11/2015

Final Integration at Wallops

~08/11/2015

LAUNCH

~08/12/2015

Contingency Launch 

 

 

 <p>
  <center><iframe src="https://www.google.com/calendar/embed?height=600&amp;wkst=1&amp;bgcolor=%23FFFFFF&amp;src=colorado.edu_9hjkgchluavtsv25rmgeu1vg68%40group.calendar.google.com&amp;color=%2323164E&amp;ctz=America%2FDenver" style=" border-width:0 " width="800" height="600" frameborder="0" scrolling="no"></iframe></center>